Overview
Retail, office, medical and restaurant construction along Edmond's Kelly Avenue arterial, scheduled around city road projects, medians and open businesses.
Project Details
Category
Area
- Edmond and the Oklahoma City metro
Next step
Service Areas
General Contractor on the Kelly Avenue Corridor in Edmond
A road crew and a building crew rarely want the same lane at the same time, and on Kelly Avenue they often work within a few hundred feet of each other. We build retail, office, medical and restaurant projects along this north-south arterial, which runs through Edmond from Memorial Road to Coffee Creek, and the schedule for every one of them has to account for what the city and the state are doing to the pavement outside the property line.
Recent history shows how active the corridor is. The city reopened the intersection of West Danforth Road and North Kelly Avenue in July 2026 after a $9 million safety project that began in September 2025, with $2.3 million from the Oklahoma Department of Transportation. The work added dual left-turn lanes, right-turn lanes, raised medians, new sidewalks west of Kelly and signals at Hawthorne Lane. Earlier, work at 33rd Street and Kelly Avenue beginning April 14, 2021 replaced deteriorated concrete panels and left one lane in each direction. For an owner, each of those projects meant detours, lane restrictions and changed driveway access.
Building while the street changes
Our rule is to learn the city's capital program before we finalize a construction schedule. A raised median can eliminate a left turn into your driveway after your building opens, and a new signal can shift the best place for an entrance. We ask the city what is planned for the frontage, adjust site design where it is still cheap to do so and tell owners how that will affect customers during construction.
Deliveries are the other pressure point. When a major intersection is reduced to one lane each direction, a concrete truck waiting to turn is a hazard and a complaint. We stage trucks off the arterial, use flaggers where permits require them and schedule pours for hours when traffic is lightest. Large steel or precast pieces arrive on a coordinated overnight or early-morning window whenever the city allows it.
Concrete is our common ground with the street
The 33rd Street and Kelly project replaced deteriorated concrete panels, and the same material governs much of what we build: paving, curb and gutter, drive approaches, dock aprons and slabs. Because we manage concrete work closely, we can talk to city inspectors in their own language about subgrade preparation, joint spacing, dowels and cure time. That experience matters on corridor sites, where driveway approaches tie into public pavement and have to be built to the city's standard.
It also helps with schedule. When a driveway cut is permitted for a specific closure window, we plan the concrete work around that window instead of waiting on a subcontractor's availability. Owners looking at larger pavement scopes can read about our parking lot construction and concrete foundations work, which use the same trade partners and quality checks.
The interchange at the north end
Where Kelly Avenue meets the Broadway Extension at Memorial Road, a $30 million state contract that began in July 2008 realigned the interchange. That history is a reminder that the corridor's geometry has changed more than once, and that older site plans sometimes assume access that no longer exists. We study the current configuration on the ground, not only in old drawings, and we review the design with the city before permit submittal. The neighboring Broadway Extension corridor page describes how we approach state-highway frontage.
South of the interchange, the corridor supports mixed commercial uses, and our South Kelly industrial area work addresses a different building type with heavier trucks and larger floor slabs.
Phasing next to open businesses
Many Kelly Avenue projects are expansions or renovations of buildings that remain open. We handle phased construction on occupied sites with temporary barriers, separate construction entrances, dust control and noise limits tied to business hours. Utility shutdowns happen at night or on weekends, with written notice to the tenants affected.
Pedestrian routes also change during roadwork. The Danforth project replaced sidewalks west of Kelly, and nearby property owners had to adjust customer paths. We maintain accessible routes throughout construction so deliveries, employees and patrons can reach the building safely.
Who we build for on this corridor
Most corridor owners fall into three groups. Property managers and investors hold multi-tenant retail and office buildings and want predictable tenant turnover, so our property management firms work focuses on base-building upgrades, roof and parking repairs and suite buildouts that minimize downtime. Restaurant and retail operators want a fixed opening date, and we coordinate with fixture and equipment vendors so the shell is ready when they are. Medical groups want clean mechanical systems and quick approvals.
Each group cares about a different part of the schedule, and we write the project plan to the owner's priority rather than to a generic template. For a landlord it may be tenant move-in. For an operator it may be a health inspection date. We ask early, and we hold ourselves to it.
Permits, signals and public coordination
Driveway permits, sign permits and building permits can have different reviewers, and projects near signalized intersections may also need traffic analysis. Edmond requires a building permit for adding to or removing structural framing, and for detached structures over 200 square feet, which includes canopies and equipment shelters on commercial sites. The city lists the 2018 ICC family of codes, and newer state-adopted editions took effect September 14, 2026, so we confirm which applies before drawings are issued.
We also notify neighbors before noisy or disruptive work begins. A phone call to the adjacent property manager costs nothing and prevents most complaints from reaching the city.
Build on Kelly Avenue with a plan for the street
Tell us the frontage and the opening date, and we will map the city's road work, your access and the construction sequence. Request a quote to get started.
Common Questions
Will road construction on Kelly Avenue delay my building?
It can, if it is not planned for. We ask the city for its schedule for the frontage during preconstruction and plan deliveries and concrete work around closures. The Danforth and Kelly intersection was closed for months of work that ended in July 2026, so we treat public projects as a normal part of the corridor.
Can raised medians change my driveway access?
Yes. Raised medians were part of the Danforth and Kelly safety project, and they can turn a full-access driveway into a right-in, right-out. We confirm what the city plans for your frontage before finalizing the site plan, then explain to the owner how the change affects customers.
Can you keep a business open during an expansion?
We do this regularly. Temporary barriers, a separate construction entrance, dust and noise control, and scheduled utility shutdowns let a store or office keep operating while new space is built. The plan is agreed in writing with the owner and tenants before work starts.
Who handles driveway approach concrete?
We do, through concrete trade partners we schedule and inspect. The approach ties into public pavement and has to meet city specifications for base, joints and cure. Managing it directly lets us build it inside a permitted closure window rather than wait on a subcontractor.
Which code edition applies to a new building on Kelly Avenue?
Edmond lists the 2018 ICC family of codes on its building code page, and the state adopted newer editions effective September 14, 2026. We confirm the edition with the building department before pricing.